Projects completed in 2018:
 
November 1, at the State Company “Gaysinsky ethanol plant”, Vinnitsa region we have launched the first in Ukraine three-adsorber revolver unit for ethanol dehydration. The nominal unit capacity is 63 tpd with stable, economical operation range from 40 tpd to 95 tpd.
 
Three-adsorber technology: – supplies heating steam evenly and smoothes pressure fluctuations on product lines, – clearly regulates the quality of the product – up to 99.999%, – uses the secondary product steam for heating the vacuum monocolumn, – improves the possibility of a deep selection of intermediate impurities.
 
The unit is combined with a vacuum monocolumn the same capacity – it’s allows to produce dehydrated ethanol, saving of 1.5 tons of heating steam per hour.
 
Projects completed in 2017:
 
July 6 at the State Company “Trostianetsky ethanol plant”, Vinnitsa region  we have launched  distillation and rectification plant for bioethanol production, capacity of 60 tpd. Specific consumption of heating steam is not more than 2.2 kg/l  of absolute product.
 
June 2 at the State Company “Gaysinsky ethanol plant”, Vinnitsa region we have launched 2nd in Ukraine under vacuum distillation and rectification monocolumn plant for bioethanol production, capacity of 60 tpd. 
 
Projects completed in 2016:
 
March 4 at the State Company “Gaysinsky ethanol plant”, Vinnitsa region at first time in Ukraine we have launched under vacuum distillation and rectification monocolumn plant for bioethanol production, capacity of 60 tpd. Specific consumption of heating steam is not more than 2.1 kg/l or 170 Nm³ of natural gas per 1 m³ of absolute product.
 
Projects completed in 2015:
 
December 16 at SC “Gaysinsky ethanol plant” at first time in Ukraine we have commissioned distillation and rectification monocolumn for bioethanol production, capacity of 60 tpd and consumption of steam of 1.7 kg/l of the crude product.
 
Projects completed in 2014:
 
LLC “Biochem groups”, Donetsk region — On February 20, a new unit for distillation and concentration of  fuel ethanol was launched as well as dewatering unit with the capacity of 25 tpd. The project uses energy-efficient technological solutions.
 
SC “Gaysinsky ethanol plant”, Vinnitsa region — On October 16, there was commissioned a fuel ethanol adsorption dehydration block with the capacity of 100 tpd. The water content of the product – 0.01%. Modernized ethanol distillation and concentration unit was put into. Steam consumption amounts 2.5 kg/l of product through the use of energy efficient technology solutions.
 
LLC “Budylsky experimental plant”, Sumy region — On October 24, a unit for distillation and concentration of ethanol with the capacity of 50 tpd was put into operation after reconstruction of thermal scheme. The steam consumption amounts 2.5 kg/l of product.